GENERAL MANAGER’S TABLED REPORT ON MATTERS FOR DETERMINATION SUBMITTED TO THE Ordinary Council Meeting TO BE HELD ON Tuesday 25 June, 2019

Page 1

 

 

 

TABLE OF CONTENTS

 

 

 

ITEM 18    REFURBISHMENT OF THE MAIN PAVILION AND LUNCHEON PAVILION AT THE MOLONG SHOWGROUND.................................................................. 2

ITEM 19    RECORDING COUNCIL MEETINGS................................................. 3   

 

ANNEXURE ITEMS

 

ANNEXURE 18.1  20190617 Annexure 1 Structural Condition Report_Molong Showground Pavilions_LC........................................ 3


ITEM 18 - REFURBISHMENT OF THE MAIN PAVILION AND LUNCHEON PAVILION AT THE MOLONG SHOWGROUND

REPORT IN BRIEF

 

Reason For Report

Authorisation of expenditure from Capital Works Reserve.

Policy Implications

Nil

Budget Implications

$190,000 from Capital Works Reserve

IPR Linkage

3.3.3.e - Maintain the council's properties to safe operational standards

Annexures

1.  20190617 Annexure 1 Structural Condition Report_Molong Showground Pavilions_LC    

File Number

\OFFICIAL RECORDS LIBRARY\PARKS AND RESERVES\MAINTENANCE\MOLONG SHOWGROUND - 1019309

 

 

Recommendation

 

THAT Council approve $190,000 expenditure from the Capital Works Reserve to carry out the recommended repair works as listed in the report to the Main Pavilion and Luncheon Pavilion buildings at the Molong Showground. 

 

 

Director of Engineering & Technical Services' REPORT

 

The Molong Showground pavilions are located on Crown land to which council is trustees.    A licence between Council and the Showground Trust operates to establish core functions. 

 

Council recently carried out detailed inspections of the Main Pavilion and Luncheon Pavilion at the Molong Showground, to ascertain the structural condition of them, and recommend any necessary repairs.    Following the inspections, it was found that a total of eight areas required repair works to return the buildings to a safe and satisfactory condition.    The majority of the damage to the structures was caused by insect infestation and inadequate building drainage.     The detailed findings and recommendations are included in Annexure 1 and the summary of the recommended repair works to are presented below. 

 

Main Pavilion

 

·    Some of the entry brickwork is in danger of falling and should be restored fully to its original condition.   This work should be done immediately as it poses a moderate safety risk to people. 

 

·    Remove flooring as necessary to allow a full inspection of the entire floor area and to allow repairs as needed such as stump replacement with concrete footings and brick piers with ant caps, bearer and joist replacement as needed.    There should be provision of wall vents along all sides of the building so that subfloor ventilation is maintained.   This work should be done immediately as it poses a moderate safety risk to people.  

·    The sagging in the entry ceiling should be immediately removed.   Adjacent termite damage in timber posts and trusses etc.   must also be repaired and treated.   This work should be done immediately as it poses a high safety risk to people. 

·    Ground regrading should also be done to prevent ponding against the building to facilitate the reduction of footing movements. 

·    Roof sheeting nails have become ineffective in several areas causing the corrugated sheeting to lift and deform.   These fixings should be replaced with suitable screws to flatten the sheeting and prevent possible leaks. 

·    Reroute the downpipes on the north- west side of the building as a charged system by running the pipes in the ground around the perimeter of the building.   This work must be done as soon as possible to mitigate the uncontrolled flooding of the sub-floor area. 

 

Luncheon Pavilion

 

·    At the ridge line area, the steel ties in two of roof frames are missing and others appear to be 20mm solid rods and these ties must be replaced.   Collar ties must be re-fastened or replaced as necessary.   The roof should be propped as needed to restore roof shape and the ties need to be fixed to maintain the roof position.   The wall top plates need to be refixed to the timber posts.   These works should be done immediately as it poses a moderate risk to people.

 

·    Near the south east corner of the building, the defective beam and rafter needs to be replaced by propping the roof.   This work should be done immediately as it poses a severe safety risk to people. 

 

The Molong Showground Society has organised 155th Molong Annual Show to be held on 22 September 2019.   It is anticipated that the Show Society will utilise the existing Main Pavilion and Luncheon Pavilion buildings during this event.   Should the recommendation of the report be approved, the repair work would be programmed and planned so that the work to correct higher risk structural repairs be undertaken first, followed by those with a lesser risk.   This work would commence immediately and therefore would have minimal or no impact on the annual show, ensuring it could proceed as planned. 

 

Following the repairs to the buildings in accordance to the recommendations outlined in the report, it is estimated, along with an annual pest eradication programme and building maintenance schedule, that the longevity of the structures will be an additional 25 years. 

 

 

ITEM 19 - RECORDING COUNCIL MEETINGS

REPORT IN BRIEF

 

Reason For Report

Authorise investigations into providing video and audio recordings of council meetings.

Policy Implications

Nil

Budget Implications

Nil

IPR Linkage

4.5.1.f - Adhere to Council's Code of Conduct and Code of Meeting Practice

Annexures

Nil   

File Number

\OFFICIAL RECORDS LIBRARY\CORPORATE MANAGEMENT\POLICY\POLICY CORRESPONDENCE - 1019321

 

 

Recommendation

 

THAT Council investigate providing audio and video recording of its council meetings.

 

General Managers' REPORT

 

Council will recall that webcasting of council meetings is a mandatory provision of the Model Code of Meeting Practice and in adopting its Code of Meeting Practice, council established a minimum level of recording council meetings, being audio recording only.

 

Further discussion with councillors and subsequent to the Mayor’s attendance of Country Mayors Association and the recent ALGA National General Assembly, indicates there is growing interest in our council providing video and audio recording of meetings.  

 

Enquiries of trade exhibitors at the recent Canberra conference indicated that suitable audio and video equipment can be sourced for approx. $21k, being within the established council budget.

 

The proposed system being a three-camera system, with individual microphones for each councillor and staff member.  A camera can be pointed at each side of the room with a third pointing towards the front desk.  Video can be split in four so that all three camera feeds are visible at once with the option to display either the live minutes or some other image on the fourth quarter.  Councillors will be required to press a button on their microphone to speak to achieve decent audio quality.  Streaming will be stopped and restarted as the meeting moves in and out of closed sessions and is controlled by the minute takers.

  


Item 18 Ordinary Meeting 25 June 2019

Item 18 - Annexure 1

 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator