ITEM 36 - Supplimentary report for Item 28 - Cudal Showground Connection to Sewer Reticulation.

REPORT IN BRIEF

 

Reason For Report

Clarify policy for connection to sewer mains

Policy Implications

Sewer policy - 93/6/98-9

Budget Implications

Nil

Annexures

Nil   

File Number

\OFFICIAL RECORDS LIBRARY\SEWERAGE AND DRAINAGE\DESIGN AND CONSTRUCTION\CUDAL SEWERAGE - 426704

 

 

Recommendation

 

THAT:

 

1.   Council defer consideration of item 28 – Cudal Showground Connection to Sewer Reticulation

 

2.   Re-visit the Sewer Policy to remove any ambiguity relating to the connection/extension to sewer mains in Rural 1 (C) and 1 (A) zones.

         

 

Director of Engineering and Technical Services' REPORT

 

Item 28 - Cudal Showground Connection to Sewer Reticulation, recommends council’s consideration for financial assistance for the connection of the Cudal Showground to the existing rising sewer mains. The Cudal Showground is in a Rural 1(c) zone and under the current Sewer policy – Sewer Main Extension Rural 1 (c) there is some ambiguity with regards to the subject land complying with the policy.

 